Haiti - Technology : The electricity grid Péligre/Port-au-Prince almost completed - HaitiLibre.com : Haiti news 7/7
 2026-2027 Electoral Calendar, latest official version





iciHaiti - Infrastructure : Public Works in Action

Obituary : Death of artist Patrick Vilaire

CFU Challenge Series U-14 : 18 Grenadiers called up (list)

Les Cayes : The Prime Minister attended Mass at Our Lady of the Assumption

CFU Challenge U14 : D-1 Our young Grenadiers in the Dominican Republic


more news


Zapping Haiti of August 17, 2026

Haiti - Petit-Goâve : Launch of the Higher Technical Education Center

Arrival in Haiti of the OAS Secretary General at the head of a high-level delegation

Haiti - FLASH : Deployment schedule for the Gang Supression Force (GSF)

Haiti - News : Zapping...


more news


Haiti - Technology : The electricity grid Péligre/Port-au-Prince almost completed
21/01/2019 08:48:41

Haiti - Technology : The electricity grid Péligre/Port-au-Prince almost completed

As part of the implementation of the national energy policy of Electricity of Haiti (EDH), the French firm « Entreprise d’Électricité et d’Équipements (EEE) », of Group "Vinci Énergies", announced that the rehabilitation works of the high voltage power lines from Péligre to Port-au-Prince in partnership with Haitian firms : "Technique, Industrie, Agriculture, S.A." (TECINA) and "Entreprise de Construction Électro-Mécanique S.A." (ECEM) which involved in the intervention more than 200 Haitian technicians are almost finished and only a few details remain to be finalized.

Recall that this work financed by the Inter-American Development Bank (IDB) to the tune of $ 23.5 million (end 2014) https://www.haitilibre.com/en/news-12768-haiti-politic-$237m-for-the-rehabilitation-of-the-peligre-transmission-line.html , concerned the modernization of the 115,000-volt, 55-km aerial and underground transmission line. This work included the replacement of cables and all insulators, the reconstruction of 5 km of a double overhead line and the installation of 16 pylons. In addition, the triple circuit (high voltage) Delmas to Lilavois link is underground, including the crossing under the River Grise at a depth of more than 20 meters.

Vivens Métellus, ECEM's Director General Delegate, believes that after these works, the Haitian firms contracted now have the expertise and are able to carry out such work alone without the help of foreign experts.

See also :

https://www.haitilibre.com/en/news-25834-haiti-news-zapping.html

https://www.haitilibre.com/en/news-23735-haiti-politic-edh-promises-18mw-more-electricity-in-may.html

https://www.haitilibre.com/en/news-12768-haiti-politic-$237m-for-the-rehabilitation-of-the-peligre-transmission-line.html