Haiti - NOTICE : Commissioning of a 3rd transformer in Canapé-Vert - HaitiLibre.com : Haiti news 7/7
 Download the revised decree and electoral calendar, published in the official journal





Rep. Dominican - 22% increase in exports to Haiti in the 1st Quarter

End of mission for Kenya

Ouanaminthe : Launch of the «Konbit Haiti Zero Waste» Program

Funding : Haiti's intervention at ECOSOC (video)

Psychosocial support for the emotional well-being of students in Haiti


more news


Zapping Haiti of April 28, 2026

IDB satisfied with the progress made by the PAPAIR program in Haiti

Mission to Strengthen Social Protection in Artibonite and Northern Haiti

MonCash from Digicel Haiti, announces a strategic partnership with Capital Bank

Police officers demonstrate and sow panic in Delmas


more news


Haiti - NOTICE : Commissioning of a 3rd transformer in Canapé-Vert
06/04/2013 09:57:45

Haiti - NOTICE : Commissioning of a 3rd transformer in Canapé-Vert

The Electricity of Haiti (EDH) informed us that it will put in operation this Saturday, April 6, a 3rd transformer of 25 MVA at the sub-station of Canapé-Vert.

"This work falls within the framework of the improvement of the quality, quantity and stability of electricity for teh customers of Bois Verna, Canapé-Vert, Juvenat, Jalousie, Downtown of Pétion-Ville, Nérette, Marlique, Péguy-Ville, Meyotte, Road of Frères, Belvil, Vivy Mitchell, Pèlerin, Laboule, Thomassin and Kenscoff.

However, to do so, the residents of these areas will be without power in the morning of Saturday, April 6, 2013, between 8:00 am and 1:00 pm," specify the Directorate General of the EDH which relies on the patience and cooperation of the Haitian population in the common efforts towards the modernization of the energy system in Haiti.